01.04.20

Installation of pre-fabricated modules at 64 Old Church Street

On a sunny spring weekend afternoon, Apt Project Leader James Ewen oversaw the lifting and installation of three modular units which make up the extension to 64 Old Church Street, a Grade-II* listed house in Chelsea.
Granted planning consent in 2018, Apt have worked with bespoke fabricators Weber Industries and Expedition Engineering Ltd, to develop the pre-fabricated modules, which came complete with insulated cladding, roofing, services, kitchen, ceilings, internal partitions and fixed joinery. 
Having been meticulously planned over a number of months, the three units were lifted in over an 8 hour period and fitted perfectly, much to everyone’s joy and relief! The on-site team are now working through glazing the facade and finishing the internal fit-out, ready for occupation in the coming weeks.

For more information, please visit our project page here 

Share